Pillar: Planning and buildings

What can I build on a plot in Spain, and how do I confirm it before buying?

Buying land·18 min read·Updated 13 November 2026
Map from the sample report: Planning: land class. The SIU places the whole plot on urban land, under the 1990 general plan; the town hall’s planning certificate confirms what may be built.Map legend: Planning: land class
Map from page 35 of 116 of the TerrenoCheck sample report, a real plot (6633007BC5963S, Xàbia/Jávea (Alicante)): Planning: land class. The SIU places the whole plot on urban land, under the 1990 general plan; the town hall’s planning certificate confirms what may be built. Line source: MIVAU · SIU. Aerial image: © Instituto Geográfico Nacional (PNOA), CC BY 4.0. See the report page
On this page

The land class or a listing calling a plot ‘buildable’ does not determine which house you may build. Ask the municipality for a written answer for the actual parcel and project, and check the plan rules, constraints and required licence. Have a qualified professional interpret them before paying arras.

Have a specific plot in mind? The report gathers the public data and official maps for it, with source and date, for €29 VAT included. Pin it on the map →

TerrenoCheck compares the selected parcel with available public planning and constraint records and identifies unresolved checks. It costs 29 € in one language or 39 € in both; project-specific buildability must be confirmed with the municipality and your professional adviser. Sample report · Choose your plot.

A plot sold as “urban” or “buildable” may still not take your house. What you can build is set by the planning that applies to the plot, together with regional law and any separate restrictions. Before you pay a reservation fee or a deposit (arras), you need to confirm three things: that your use is allowed, how much and where you can build, and whether urbanisation duties remain. This page explains how to get that answer in writing and what to agree while it comes.

Where to find out what you can build

Start at the town hall’s planning department (Urbanismo). Bring the cadastral reference, a plan of the boundaries and a description of what you want to do. Do not just ask whether you “can build”: say house, extension or change of use. If there is already a building, also ask whether it is fuera de ordenación (outside the plan), because that limits the works.

State law gives everyone the right to access planning information and to be told in writing, within a reasonable time, the planning rules and conditions for a given property (TRLSRU, article 5.c and 5.d). Ask for the planning report, certificate or cédula procedure and its fee, and keep the receipt and the full answer.

The town’s map viewer or the SIU viewer help locate the zone. To decide on the purchase you also need the written rules and the area’s sheet, if there is one. If the seller hands over an old document, check that it still describes the rules in force and the same plot.

PGOU, normas subsidiarias or a newer plan?

Look for the town’s general plan, which may be called a PGOU, or Normas Subsidiarias (NNSS). Do not dismiss NNSS as old: in Andalusia, instruments predating the LISTA stay in force until carried out or replaced (DT 2ª).

Ask for the plan in force, its amendments and any development planning: a plan parcial, plan especial or estudio de detalle may also apply. Ask whether any instrument must still be approved before a licence can be sought. Read the map with the rules: the colour marks an area; the ordinance sets its uses and conditions.

Also ask about licence suspensions or changes in progress: State law requires approval and amendment files to identify areas where planning is suspended and for how long (TRLSRU, article 25). A draft of a future plan does not prove you can build under it today.

Classification and zoning are not the same

Classification (clasificación) puts the land in a class. Zoning (calificación) sets its use and conditions: residential, public facilities or other, with building type and parameters. In the Valencia region, detailed planning covers sub-zones with their ordinances, detailed uses, net floor-area index and plot rules (TRLOTUP, article 35).

State law also has two basic situations, rural and urbanised, which are not the plan’s classes: land awaiting completion of its urbanisation stays rural (TRLSRU, article 21). Nor confuse the Catastro’s “urban”, which follows its own law, with a permission. If you are unsure about classes, read the guide on rustic, urban and urbanizable land.

Listing saysWhat it meansWhat it does not proveFirst step
“Urban”The plan’s class, or the Catastro’s tax class.That it is a solar, which use is allowed or how much you can build.Ask for the plan’s class, zoning and ordinance in writing.
“Residential”A broad use in the zoning.That a detached single-family house is allowed.Ask for the detailed use and the exact ordinance.
“Buildable: 0.5 m²/m²”A floor-area index, net or gross.That the whole listed area counts, or that the floor area fits.Architect: area used, net or gross index, counting rules.
“Project approved”Possibly a licence, possibly only a request.That the licence is in force, for this plot and this house.Ask for the licence decision and its dates.
“Room for two houses”Floor area left over.That the plan allows two homes, or that the plot can be split.Ask for the maximum number of homes and the split rules.

Each phrase in the listing becomes a written question. Sources: BOE, Catastro Act, article 7; BOE, State Land Act (TRLSRU), article 26.2. Accessed 30 October 2026.

How much can you build, and does the house fit?

Ask an architect for a feasibility sketch on the real boundaries, stating which document each figure comes from and which plot area is used. Before applying a net index, clarify alignments and any land given up for roads: not all the advertised area has to count. If boundaries or levels are uncertain, order a topographic survey.

SIX LIMITS CHECKED TOGETHERFloor area (edificabilidad)Countable floor area per m² of land (m²t/m²s)Coverage (ocupación)The building’s footprint on the plotSetbacksDistances to the street, the sides and the rearHeightMetres and number of storeys; both applyMinimum plotRequired area, frontage and shapeHomesMaximum number or density, if the plan sets one
The figures and how they are counted come from your zone’s ordinance, not the listing. Source: BOE, Valencian TRLOTUP, article 35. Accessed 30 October 2026.

Floor area (edificabilidad) caps the countable floor area, often in m²t/m²s. A net index applies to the plot; a gross one to an area such as a sector: do not apply a gross index to the cadastral area. With a net index, net area × index = maximum countable floor area, and then you check whether it fits within the other limits. Countable area is not usable area: ask how porches, covered terraces, basements and outbuildings count.

Coverage (ocupación) caps the building’s footprint on the plot. A house can respect the floor area and still cover too much land. Check the rules on overhangs and below-ground building.

Limits that apply togetherPlot with a dashed setback envelope and a building footprint. Coverage, counted floor area and height must also be checked. This is not building consent.Limits that apply togetherDetached-building examplePlot · boundariesBuildingfootprintStreet · plot frontageDashed: setbacks in this exampleSchematic only, not to scaleOcupación · coverageHorizontal building projection.Not the sum of floor areas.Edificabilidad · floor-area limitNet area × net coefficient.Counted floor area; apply theordinance's counting rules.Also checkHeight, storeys, minimum plot size;plot frontage and shape;density and dwelling count.The house must satisfy all the limits.This drawing does not prove buildability.
Example of a detached building, not to scale and with no regulatory values. Not every ordinance requires setbacks from every boundary, and the footprint drawn does not prove the plot can be built on. Source: BOE, Valencian TRLOTUP, article 35. Accessed 30 October 2026.

Setbacks and height: where they are measured from

Setbacks (retranqueos) decide where the building can stand. Tell apart the street boundary, the sides and the rear, and ask for the official alignment if in doubt: the wall you see may not match the plan’s line.

Height may be capped in metres and in storeys, and both apply where the ordinance sets them. On a slope, the reference point changes the result: the architect must justify it with the applicable ground levels. Do not count on gaining a storey through fill without checking the rules.

Minimum plot, number of homes and splits

Meeting the minimum area is not enough: check frontage and shape too. A narrow plot can exceed the minimum and have little room left after setbacks. Ask for the maximum number of homes and density, if the plan sets one: spare floor area does not allow dividing a house into separate homes.

If buildings already exist, the study must include them in the calculation; do not assume you can demolish and rebuild with the same volume. If you are sold a portion, each resulting plot must meet the law and the plan, including sales of shares with exclusive use of one part (TRLSRU, article 26.2). When a plot uses up its floor area or the rest falls below the minimum, the licence is notified to the Land Registry so that the plot is recorded as indivisible (article 26.3).

What the certificate or cédula should say

Ask for a document on the property in your plan and the planned use, so the architect can work without rebuilding the rules from phrases in the listing. You can adapt this wording:

Wording for the request (send it in Spanish). Solicito información urbanística escrita de la parcela con referencia catastral [referencia], delimitada en el plano adjunto. La actuación prevista es [descripción del uso y de las obras]. Indiquen el planeamiento vigente y sus modificaciones, la clasificación y categoría del suelo, la calificación y la ordenanza aplicable; confirmen el uso previsto, la edificabilidad, ocupación, separaciones, altura, número de plantas, número máximo de viviendas, densidad y condiciones mínimas de parcela, con sus reglas de cómputo; si tiene condición de solar, qué planeamiento o urbanización falta y qué deberes pendientes asumiría el comprador; las afecciones y autorizaciones sectoriales, suspensiones de licencias, modificaciones en tramitación y expedientes urbanísticos que afecten a la finca; y el procedimiento exigible para la actuación descrita.

There is no single national validity. In Andalusia the cédula is sent within one month at most from entry in the town’s electronic registry, unless the town sets less; it is for information, does not bind the authority and stays valid while the planning it relies on is in force, six months at most. No answer does not count in your favour (LISTA Regulation, article 3).

In Catalonia the planning certificate is notified within one month. For a buildable property it is valid for six months from notice, and licences applied for in that period, with no incurable defects and matching the rules in force when the certificate was requested, must be granted (TRLU, article 105). That protection does not make the certificate a licence. More in the guide to the cédula urbanística.

Building licence or compliance declaration?

The rules decide which works need a licence and which may go by compliance declaration (declaración responsable) or prior notice; you cannot replace a required licence with a declaration. Murcia lets you apply for a licence voluntarily for works outside its list (LOTURM, article 263.3), and in the Canaries the town hall must process a licence application even for works under prior notice (LSENPC, article 332.3).

A new home needs a technical project: the exception for simple single-storey buildings excludes residential use (Building Act, LOE, article 2.2.a).

A compliance declaration states that you meet the requirements and hold the documents to prove it. It is not an approval after reviewing a project: it remains subject to checks and inspection, and a material inaccuracy, falsehood or omission stops the works, with whatever liability follows (Law 39/2015, article 69).

A filing receipt does not prove the works are allowed. Do not buy assuming a declaration will cover a house the plan does not allow. In Andalusia, any prior approval or report required by sector rules must be obtained before the declaration is filed (LISTA, article 138.4). Sources: BOE, LISTA, article 138; BOE, Law 39/2015, article 69. Accessed 30 October 2026.

Ask for the study to identify constraints from watercourses and flooding, the Coastal Law, nature or heritage, with the competent body and the approval needed. Residential zoning does not settle those restrictions.

What changes between regions

RegionWhat to checkReference
AndalusiaThe LISTA has urban and rustic land. A licence is the starting rule with legal exceptions; article 138 lists works under a compliance declaration, among them small works without a project and certain works on existing buildings.LISTA, articles 137–138
Valencia regionNew buildings need a licence (article 232). The listed renovations follow article 233; some in its second paragraph need a certificate from an administrative certification body or professional college.TRLOTUP, articles 232–233
Murcia regionArticles 263 and 264 separate licence and declaration. The exception for small, simple new buildings is for non-residential, non-public uses only: it does not cover a house.LOTURM, articles 263–264
CataloniaA licence for new buildings and works with a project; prior notice (comunicación previa) for certain works without a project, with exceptions for location and protection.TRLU, articles 187 and 187 bis
Balearic IslandsLicence and prior notice are separate. Island councils may regulate the scope of prior notice within the legal limits: check the rule for the island and the town.LUIB, articles 146 and 148
Canary IslandsNew buildings need a licence; certain renovations without extra volume or floor area go by prior notice. The Canary government may change the lists by decree: check the rule in force for your works.LSENPC, articles 330 and 332

Do not rely on an answer given for another region. Sources: BOE, LISTA; BOE, TRLOTUP; BOE, LOTURM; BOE, TRLU; BOE, LUIB; BOE, LSENPC. Accessed 30 October 2026.

A prefabricated house does not avoid checking use and procedure: the Valencian, Catalan, Balearic and Canary laws list it expressly among works needing a licence. On Andalusian rustic land, a detached house with no farm link also needs prior approval and pays a compensation levy of 15 % of the construction budget (LISTA, article 22).

Is an urban plot ready to build on?

Ask whether it is a solar (a serviced building plot) and, if not, what is missing. In Andalusia a solar needs the infrastructure and services in the plan and at least paved urban access, lighting, and water, sewerage and electricity with enough capacity (LISTA, article 13.3). A pipe or a pole nearby does not prove that. If the plan speaks of “consolidado” or “no consolidado” urban land, the guide to consolidated and non-consolidated urban land explains the duties each category carries.

A sale does not erase planning duties: the buyer steps into them, and the deed must state any outstanding duties and obligations (TRLSRU, article 27). Give your lawyer the deed and a recent nota simple, which is for information only (Mortgage Law, article 222.5). The absence of an entry does not replace asking the town hall.

Check easements and other private limits too. A licence is granted without prejudice to ownership and to third-party rights (Local Services Regulation, article 12.1): meeting the plan may not be enough to build the design.

Costs and timing before the deposit

Ask for the tax ordinance. There may be fees for issuing documents and for the licence or for checking a declaration, and the construction tax (ICIO) can also apply to works under a declaration or notice (Local Finance Act, articles 20.4.h and 100).

CheckWhoCost and time
Identify the plot; get the plan and rules in forceYou and the planning departmentDocument fee per ordinance; ask for the deadline in writing
Written planning information on the planned useTown hallLocal fee; Andalusia: one month at most; Catalonia: notified within one month
Layout, calculations and the state of existing buildingsIndependent architectQuote first; deadline agreed from receipt of all documents
Deed and nota simple against solar status, access, private rights and pending dutiesLawyer, town hall and architectFees quoted; settle before committing to the price
Procedure, prior planning approvals and sector approvalsArchitect and the authoritiesEach fee and deadline for your case
Purchase condition and refundYour lawyerClose the wording before any deposit

Keep town hall fees apart from professional fees and urbanisation costs. Source: BOE, Local Finance Act, articles 20.4 and 100. Accessed 30 October 2026.

Three hypothetical scenarios

These are invented examples to show the method, not real plots.

Hypothetical example

1. “Urban, 600 m², index 0.5”

Imagine the index is gross, for the sector, and 80 m² of the plot are reserved to widen the street. The real floor area may end up well below the 300 m² the listing implies. Ask for the area sheet and the alignment before making an offer.

Hypothetical example

2. A narrow plot that meets the minimum

Imagine 400 m² with 12 m of frontage and 3 m setbacks on each side. That leaves 6 m of width for the house. The plot meets the minimum, but the project you want may not fit. The architect’s sketch will tell you in a day.

Hypothetical example

3. An urbanizable sector “about to be developed”

Imagine the plan parcial is approved but the urbanisation project is not. Until urbanisation is finished, the law treats the land as rural, and the buyer takes on the outstanding duties. Ask for the stage, the timetable and the cost per metre before the deposit.

When to hold back the deposit

FIVE SIGNALS BEFORE YOU PAYStopThe house depends on a plan change not yet approvedStopThe certificate covers another plot or another usePauseOnly the listing, the IBI bill or a Catastro captureConditionDeposit tied to the information, the approval or the licenceProceedUse allowed, house that fits and urbanisation priced
A red signal is a reason not to pay yet. It is not a legal conclusion. Source: BOE, State Land Act (TRLSRU), articles 11 and 27. Accessed 30 October 2026.

The list does not replace a lawyer. It tells you whether you can pay now or which document is still missing.

What to write into the arras contract

The contract should name the project or use the purchase depends on, the documents required and the acceptable result. Decide with your lawyer whether the condition is favourable information, a prior approval or the licence: a condition based only on information can be met even if the licence is later refused. Set a deadline, any extension and a full refund if it is not met or no answer arrives.

Asking for a certificate does not by itself entitle you to your deposit back. For an earlier reservation, have whoever receives the money accept the condition, and agree what happens to the agency’s commission. More in the guide to the arras contract.

The buyer’s sequence before the deposit

THE DOCUMENT CHAIN1 · Plan and referenceThe exact plot, with its real boundaries2 · Plan and ordinancePlan in force, amendments and the area’s sheet3 · Written informationCertificate, report or cédula on the planned use4 · Architect’s studyLayout, calculations and the procedure required5 · Deed and nota simpleLawyer: access, charges, duties and third-party rights
The viewer finds the zone; the answer is in the written rules and the study. Sources: BOE, State Land Act (TRLSRU), article 5; BOJA, LISTA Regulation, article 3. Accessed 30 October 2026.
  1. Identify the plot by its cadastral reference and a plan of its boundaries.
  2. Ask the town hall for the plan in force, its amendments and the zone’s ordinance.
  3. Request written planning information on your specific use, with the wording above.
  4. Have the architect draw the layout sketch and name the procedure required.
  5. Have the lawyer compare deed and nota simple with solar status, access, charges and duties.
  6. Ask about fees, ICIO and any urbanisation cost.
  7. Sign the arras only with the condition, a deadline and a full refund.

Questions to send before money moves

  1. Which plan governs the plot, and what amendments does it have?
  2. What classification, zoning and ordinance apply?
  3. Is my use allowed, and in which building type?
  4. Which floor area, coverage, setbacks and height apply, and how are they counted?
  5. How many homes are allowed?
  6. Is it a solar? If not, what is missing and who pays?
  7. Are licences suspended or plan changes under way?
  8. Which sector constraints apply and which approvals do I need?
  9. Licence or compliance declaration for my works?
  10. What happens to each payment if the answer does not arrive or is unfavourable?

The figure in the listing is a question, not a permission. Keep the ordinance, the town hall’s written answer and the architect’s sketch together, and compare the price with what you can really build.

This guide is general information on the rules in force on the date each source was checked. It is not legal advice: for a specific purchase, ask a lawyer or the notary. Written and reviewed by the TerrenoCheck team (Kandyb Studio, Paweł Kandybowicz, responsible for the content). If you find a mistake, write to us and we will correct it.

Common questions

How do I find the exact floor area allowed on my plot?

Ask the town hall for the ordinance and the rules for the identified plot. The architect must check the area used, the index and the counting rules together with coverage, position and height. The listing’s figure is not enough.

Can I build if the Catastro says urban?

That does not grant a licence. The Catastro class follows the Catastro Act (article 7); you need to confirm the planning, the use and whether the conditions for building are met, including any outstanding urbanisation.

Does the planning certificate guarantee the licence?

It is not the licence. Its effect depends on the region: the Andalusian cédula is for information; the Catalan certificate can protect a licence application made within six months if it meets the conditions of TRLU article 105.

Can a small or prefab house go ahead without a project?

Size does not exempt a new home from a project: the LOE exception for simple buildings excludes residential use (article 2.2.a). For a prefab, also confirm the planning procedure and that residential use is allowed.

Can I extend a house that already appears in the deed?

The deed does not authorise an extension. Ask for the planning history and have the building’s status, spare floor area and permitted works checked. The same applies to turning a store into a home.